Reports of previous projects - by: mcanuto

$
0
0
Hello,

I have un issue and would like to know if it is the normal behaviour:

I'll try to explain :

I have a resource that was the Teamleader of a project until june. I put an end date (28/06/2019) to the allocation to that project. Since that, he can't see the data from that project in the reports anymore, even for the previous months. This is a problem because he can't even print a timesheet of may, if he needs, his timesheet is not complet, he only gets the information of other projects.

How can I solve this? Am I doing something wrong?

Thank you for your answers.

Regards,
MCanuto