Proper understanding of "dates" related to activities, tasks, etc - by: needhelp
I am having real problems understanding how the dates are functioning in the software; consequence is that I cannot close tasks and activities; for example: I set an action on Monday - Initial due...
View ArticleKANBAN: Filter list by Project - by: Charles.Baudron
When i open the list of Tickets, if one project is selected, the list is filtered. Do the same when i open a list on KANBAN
View Article[SOLVED] Unknown column 'testcase.idProductOrComponent' in 'on clause' - by:...
Hello, In the "test case" screen, if I select the column "Product or component" to be displayed, none of the test cases show up and I get this error in the logs :2017-06-23 12:47:41.073 ***** ERROR...
View Articlecustomization screen - by: dep@eca.fr
is it possible to mandate the work assigned when the status change of an activity?
View ArticleTéléchargement du plugin "Traduction des paramètres FR" - by: alaind83
Bonjour Bien que je dispose d'un compte et que je parvienne à me connecter sur le site, je n'arrive pas à télécharger le plugin "Traduction des paramètres FR" car sur l'espace boutique mon identifiant...
View ArticleMobile App - by: 0SV?s?4T
Dear babynus, I am new to ProjeQtOr and already fond of it. Great work!. Yet I am missing dearly the "Stopwatch" functonality from my old application PHProjekt (Mayflower GMBH v6.2.1, maintenance...
View Articlesql id wbs project & activity - by: chriscool
hello where the information of this field WBS Id on table sql ? wbs id on project and activity ? select * from project i retrieve this information on sortorder but is not real value i think ? thank you...
View ArticleIs a "construction work" (chantier in french) rather a project or an...
Hello, First I want to thank you for your tool which may - juste starting to discover it - be a great help to my current project. I wonder how to implement the "chantier" notion in projector: would it...
View ArticleHow to create another default calendar? - by: NarayanAras
Hi We have two teams, one working in India and the other working in the Gulf. I need to create another calendar, which differs from the default calendar in the following ways: 1. There is a time...
View ArticleCopy a project - by: Damien Gozillon
I created Default Projet or Model (Modele in French). The problem is I cannot copy it. I have an error message (see attachement). I put a date and charge in every task (it should'nt be necessary in a...
View Article[SOLVED] sql id wbs project & activity - by: chriscool
hello where the information of this field WBS Id on table sql ? wbs id on project and activity ? select * from project i retrieve this information on sortorder but is not real value i think ? thank you...
View ArticleUsers - fields "email" and "password" are automatically filled whenusing...
Hello, When going on the users panel and when selecting one user, the field used for "email" and "password" are automatically filled with the connected users credentials. If you pay no attention when...
View ArticleEmail delivery : SpamAssassin does not like that - by: Kitcat711
Hello, SpamAssassin is noticing that our email do have these problems: HTML-only message, but there is no HTML tag => add the tag Message only has text/html MIME parts => add the text/plain...
View Article[SOLVED] Activities makred as done on creation - by: mendo15
Whenever I create a new activity, at the first save, the Done checkbox is automatically check-marked and the date of creation is marked as the done date/ please advise.
View ArticleFilter projects by organization - by: louisc
Hello, In our company we have several departments who have joined Projeqtor. Each department follows his own projects, and some projects are shared between the organizations. Currently, there is no...
View ArticleSynology - Projeqtor - by: Salut75
Hello, Do you think about a Projeqtor package on Synology plateforme ? Best Regards
View ArticleKPI : SQL error - by: louisc
Hello, Looking at the logs while I can't manage to get consolidated KPI, I found a lot of Exceptions concerning essentially h.year and h.month column not found in the database. 2017-04-12 17:38:11.508...
View ArticleView planned activities in a calendar - by: mendo15
Hello, Is it possible to see planned activities (an installation that will take weeks) with their associated resources in the calendar? Thanks
View ArticleHow to specify "for the duration of this activity"? - by: NarayanAras
I have an activity, which has two resources assigned to it. The main effort comes from the first resource. The second resource is support-provider, and he is lightly engaged with that activity as long...
View Article[SOLVED] Problem with planned end date - by: #Chris
Hello, I have planned a project which should have started last year in August. The validated start date was 22/08/2016 and the end date 30/09/2016. But now we could only start at 13/06/2017. So I set...