We have a critical issue about "planned date" milestone:
- When the milestone is "fixed" and validated or delivered:
The "planned date" shall be the same date than the "real date" when "done" is checked.
Now, the "planned date" corresponds to the "validated date" when the milestone is fixed.
- When the milestone is "floating" and validated or delivered :
The "planned date" shall be the same date than the "real date" when "done" is checked. During planification of the projet, even if the milestone is done, the planned date is updated and does not corespond to the real date. See an example attached.
To summarize, for all milestones, if "done" is checked ==>planned date" = "real date".
- When the milestone is "fixed" and validated or delivered:
The "planned date" shall be the same date than the "real date" when "done" is checked.
Now, the "planned date" corresponds to the "validated date" when the milestone is fixed.
- When the milestone is "floating" and validated or delivered :
The "planned date" shall be the same date than the "real date" when "done" is checked. During planification of the projet, even if the milestone is done, the planned date is updated and does not corespond to the real date. See an example attached.
To summarize, for all milestones, if "done" is checked ==>planned date" = "real date".