Hello,
I have a mini project with about 10 task and 207 assigned hours ( seee screen capture) and when i produce the S curve , I see only 29 hours for the coût budgetiser du travail planifié (see s curve figure). Shouldn`t the 207 assigned hours be equal to the planned value ( coût budgetiser du travail planifié)? Am I missing something?
Regards
Thanks
I have a mini project with about 10 task and 207 assigned hours ( seee screen capture) and when i produce the S curve , I see only 29 hours for the coût budgetiser du travail planifié (see s curve figure). Shouldn`t the 207 assigned hours be equal to the planned value ( coût budgetiser du travail planifié)? Am I missing something?