When I create a ticket on activity for resource #1, when this resource put some job on ticket, the ticket appears under activity.
I would like to block the possibility to enter time on the activity. Is it possible?
or is it possible to block the entry time on a type of project and not others ?
In fact, i would like that resource can input time on administrativ project on activity but only on tickets for other project.
I would like to block the possibility to enter time on the activity. Is it possible?
or is it possible to block the entry time on a type of project and not others ?
In fact, i would like that resource can input time on administrativ project on activity but only on tickets for other project.