Hello,
I noticed that an expense with state "canceled" (ie : state parameter set to "Handled" = not, "Done" = Not, "Closed" = Yes and "Cancelled" = Yes) is computed as "Handled" in project expense report.
See attached image, expense of 52 822,81 € was cancelled but shown on total costs per month report.
Regards,