When i copy an activity to a milestone, the validated cost follows form the activity into the milestone, if i'm right, there should not be any amount in a milestone.
Is this a normal behavior ?
Now, in global planning, we are stuck with milestone that have a validated cost.
How can i get rid of the amount in the validated cost column.
I'm able to delete the amount in the validated cost column from the planningelement table directly into the database, but i don't know if it's the right way to do it or if it will impact somethings else.
If i create a milestone without using the copy feature, there is no amount in global planning.
Can you help,
Regards
V8.0.3
When i copy an activity to a milestone, the validated cost follows form the activity into the milestone, if i'm right, there should not be any amount in a milestone.
Is this a normal behavior ?
Now, in global planning, we are stuck with milestone that have a validated cost.
How can i get rid of the amount in the validated cost column.
I'm able to delete the amount in the validated cost column from the planningelement table directly into the database, but i don't know if it's the right way to do it or if it will impact somethings else.
If i create a milestone without using the copy feature, there is no amount in global planning.
Can you help,