[SOLVED] Limit the hours of a resource assigned work in activity. - by: DEngine

$
0
0
Hi!

I'm facing a problem. When I assign a resource to activity and want to set hours of assigned work, I will get error at some situations.
If the quantity of hours is less 10,000 hours, it will be good.



But if this quantity is equal or more than 10,000h, I will get error.



Can I change this limit? If yes, how?

Thanks.