Hi
Projeqtor Version V7.4.3
Here is the situation
I have created a team which include 4 team member. Name : Team1
I have Allocate this team to a project
I’m creating an activity for this project, i’m assigning the Team : Team1 to this activity.
So far everything is ok, all 4 members can see theire activity.
The issue is in the TimeSheet, in their TimeSheet, they see all the activities but the project related to those activities, does not appear even if the team is assigned to the projet.
The only way for the team member to see the project in TimeSheet is to allocate the ressource in the project.
Is it normal that i have to assign the ressource even if he his a part of the team that is already assigned to the project ?
Regards
Projeqtor Version V7.4.3
Here is the situation
I have created a team which include 4 team member. Name : Team1
I have Allocate this team to a project
I’m creating an activity for this project, i’m assigning the Team : Team1 to this activity.
So far everything is ok, all 4 members can see theire activity.
The issue is in the TimeSheet, in their TimeSheet, they see all the activities but the project related to those activities, does not appear even if the team is assigned to the projet.
The only way for the team member to see the project in TimeSheet is to allocate the ressource in the project.
Is it normal that i have to assign the ressource even if he his a part of the team that is already assigned to the project ?
Regards