[SOLVED] Manual task advance and state synchronization - by: jmmbb

$
0
0
Hello,

since V7.2 we can input avancement for task with fixed duration and no assignation.
That great for organization where we don't use real work.
But there are two improvment you can made :
- when advancement is set over 0%, is it possible to set state to the first "handled" status in the workflow.
- when advancement is set to 100%, set state to the first "done" status in the workflow.

By the way, synchronization for real date will be fine :
- setting the first "handled" status set real start date to status date
- setting the firts "done" status set the real end date to status date.

Regards,