Quantcast
Channel: ProjeQtOr free project management software - ProjeQtOr free project management software - Recent Topics - ProjeQtOr
Viewing all articles
Browse latest Browse all 6784

What is the best way to allocate time for periodic task - by: BatmanTheBlind

$
0
0
Hello,

I want to allocate a certain amount of time each week for specific periodic task. For exemple : I need to define 2 days per week on Technical Support. These days may or may not be used, but I want to allocate them just in case.
But I've two problems about this :
  1. Is there a way to define the Activity once and define a periodicity ? For now, I make a copy of the task each week but it is very time-consuming.
  2. Is there a way to assign "one ressource of a specific Team" ? My need is to tell to ProjeQtor "I want to keep at least 2 day of work free on this team in case of Technical Support to do but whatever the resource is".

To give another exemple, in the same way, I would like to allocate a specific number of days on summer to anticipate leave days that are not already ask by my team.

Thank you for any advice you could give !

Viewing all articles
Browse latest Browse all 6784

Trending Articles