[SOLVED] Overall progress? - by: pavilonsxx

$
0
0
Hi all,
I have some questions for help
1. Overall progress is entered manually or automatically, when creating projects, to select how value is reasonable? Thanks to explain in more detail.
2. If there is activity ahead of schedule, projeqtor will show how? For example, user A responsible activity X, is assigned 3 date but actually only 2 date the user A has completed the activity, so how does the user A to enter into real work allocation?
Thanks for help!