I try to find the answer by myself, using this forum or the demo project. But I still can't find the solution...
I'm creating an activity, and when I assign the workload to a ressource, I would expect to get starting and ending planned date to be calculated automatically.
Unfortunately, this is not the case (see attached picture). So I guess I'm doing something wrong...
I saw in many post that I needed to run a planning calculation, but I can't find this action, and when I search this in online help, I get no result.
So if someone could help...
Thx a lot !
I try to find the answer by myself, using this forum or the demo project. But I still can't find the solution...
I'm creating an activity, and when I assign the workload to a ressource, I would expect to get starting and ending planned date to be calculated automatically.
Unfortunately, this is not the case (see attached picture). So I guess I'm doing something wrong...
I saw in many post that I needed to run a planning calculation, but I can't find this action, and when I search this in online help, I get no result.
So if someone could help...
Thx a lot !