Hello,
One Project Manager in my company has a problem with an activity which has a strange behavior with assigned, planned and real work.
Here is the situation
The ressource assigned has 0,1d assigned and 0,8d real work
But if I search in the menu "Real work allocation" for this ressource, there is no real work input.
When I search for this ressource in the different reports to found, for this activity, if real work is allocated, I don't find anything.
What I would like to do is to have no 0 in assigned, real work for this ressource, and for the activity too, to be able to suppress this activity.
How can I do that ?
Thanks for a little help
One Project Manager in my company has a problem with an activity which has a strange behavior with assigned, planned and real work.
Here is the situation
The ressource assigned has 0,1d assigned and 0,8d real work
But if I search in the menu "Real work allocation" for this ressource, there is no real work input.
When I search for this ressource in the different reports to found, for this activity, if real work is allocated, I don't find anything.
What I would like to do is to have no 0 in assigned, real work for this ressource, and for the activity too, to be able to suppress this activity.
How can I do that ?
Thanks for a little help