Hello,
I continue my tests from a full new installation of the v6.1.3.
I created a project with validated date from 03/04 to 28/04, with a single activity for the moment, from 05/04 to 12/04
I allocate 2 ressources on this activity, one for 1 day and the second for 2 days.
I see now that the duration of the activity stay 6 days and not 3 days (like in v6.1.1) and find it good![:-) :-)]()
I decide also to upgrade my "PreProd environnement" which is in 6.1.1 to 6.1.3 to test this operation mode in my environnment....but it doesnt work like in the new 6.1.3 environnment![:-( :-(]()
And after Real allocation input four the user1, the field "Planned" is not updated : it is not the same in v6.1.1
Is there some parameters I need to put to have this operation mode ? It would be great because I find it is the right operation mode (workload don't have to change duration on a project, it can be really two different things)
Thanks
I continue my tests from a full new installation of the v6.1.3.
I created a project with validated date from 03/04 to 28/04, with a single activity for the moment, from 05/04 to 12/04
I allocate 2 ressources on this activity, one for 1 day and the second for 2 days.
I see now that the duration of the activity stay 6 days and not 3 days (like in v6.1.1) and find it good

I decide also to upgrade my "PreProd environnement" which is in 6.1.1 to 6.1.3 to test this operation mode in my environnment....but it doesnt work like in the new 6.1.3 environnment

And after Real allocation input four the user1, the field "Planned" is not updated : it is not the same in v6.1.1
Is there some parameters I need to put to have this operation mode ? It would be great because I find it is the right operation mode (workload don't have to change duration on a project, it can be really two different things)
Thanks